Testing begins on Bursa high-speed rail line, Ankara trip to take 2 hours 15 minutes

Transport Minister Abdulkadir Uraloglu said the Osmaneli-Bursa section has completed infrastructure and superstructure work and entered the testing phase.

Sources: Olay Gazetesi, Mardin Life, Yeni Kocaeli3 sources ↓|· 1 min read
Testing begins on Bursa high-speed rail line, Ankara trip to take 2 hours 15 minutes
Photo: Olay Gazetesi

KEY POINTS

  • Infrastructure and superstructure work on the Osmaneli-Bursa section is complete
  • Testing and certification are underway before the line enters service
  • Travel time between Bursa and Ankara or Istanbul will drop to 2 hours 15 minutes
  • The overall project is 83.08 percent physically complete

Transport and Infrastructure Minister Abdulkadir Uraloglu announced that infrastructure and superstructure work on the Osmaneli-Bursa section has been completed and testing has begun. He said the line will connect Bursa directly to Turkey's high-speed rail network once testing and certification are finished.

Testing is proceeding in stages. Static catenary measurements and track geometry measurements were completed in September and October, while signaling power system tests started in October.

“We will make our line ready for operation with tests.”

— Abdulkadir Uraloglu

Catenary hot run tests were carried out this month, and dynamic acceleration tests and dynamic catenary measurements will also be conducted. Future stages will include signaling concordance tests, European Train Control System (ETCS) tests, and GSM-R railway mobile communication system tests.

Integration checks between the Osmaneli-Bursa line and the existing Ankara-Istanbul high-speed line will also be performed. The minister emphasized that comprehensive checks are necessary to put the line into safe operation.

Once completed, the line will link Bursa directly to the Ankara-Istanbul high-speed line via Osmaneli. Travel times between Bursa-Ankara and Bursa-Istanbul are expected to fall to 2 hours and 15 minutes.

The overall Bandırma-Bursa-Yenişehir-Osmaneli High-Speed Rail Project has achieved 83.08 percent physical progress. Construction work on the Bursa-Bandırma section is continuing, and the project will serve both passenger and freight transport.